Serge Krauss · Dec 21, 2003 05:13 PM
#0 sourceThe Long Story:
I have built most of a Tom Morris D-tube style wing that, up to leading-edge planking time, was very rigid and straight. It is like a new Millenium wing, except that rib slices have specific section contours and were built up into ribs before being rotated into the spar slots. The trussed spar, leading edge, and trailing edge are like those shown on p. 51 of the current Stunt News. 41 Ribs and l.e. stub ribs are spaced 1.25" apart ahead of the spar, while rib spacing behind the spar is 2.5", with diagonal bracing. All ribs are 1/16", as is the 6 lb/ft^3 sheeting.
I ended up diverting from my planned in-jig attachment with white glue, per Tom Morris, because I couldn't get the 6-lb sheeting into good contact with the ribs with Windex and an entire set of iron weights. The glue set up too fast, and the sheeting dried too fast. I ended up cracking the first sheet loose (pretty easy) and reattaching it with CA, doing some of the work out of the jig. I again sprayed Windex on the outside sheeting surfaces to soften and warp the sheeting toward the spar. I had to do this after tacking the sheeting dry to the l.e. spar (despite fears that this would induce a warp) since I couldn't keep the sheeting straight when damp (destroyed one trying).
The short Story:
I now have three of the four l.e. sheets attached (both bottoms and the upper right) and a twist that has the right tip leading edge almost 1/8" ( 1.4 degrees) low, when the center and other corners are jigged level without weights. The wing is so stiff that it takes over 20 oz of iron weights to hold the right tip trailing edge down when the leading edge is jigged up and level (some extra weights required at root too). Since this process was taking so long, I felt as though I had to jig the wing before applying the opposite sheeting - maybe a mistake.
I have not attached the upper right sheeting to the ribs yet (just to l.e. and spar), but contact with ribs is good so far.
Well, here are the questions:
1) What is generally the net effect of dampening wood with windex? It definitely swells when wet, but does it dry smaller or larger than its original size? A leftover piece bowed away from the once damp side seems to point to net expansion. This would influence strategy.
2) Should I finish attaching the upper right sheet to the ribs while in jig, but before again dampening anything or otherwise proceeding?
3) Should I sheet the upper left before trying to straighten the right wing half?
4) Should I dampen all, or just selected parts to try to jig the wing back into shape?
I considered dribbling CA over interior sheeting surfaces to stabilize the sheets in tension, but this seems extreme and heavy. There will also be a built up triangular tube (sheeted) trailing edge structure extending behind the current aft jigged spar; it might stabilize things some.
Or should I just give it up to lessons learned and try to figure out how to get Tom's instructions to work for me on some later project? This is a very labor intensive and - 'til now - well crafted wing with accurate airfoils. I really hate the idea of scrapping it.
All advice welcome - although I know that I've not glued wisely.
'just want to cover all the bases. Thanks for whatever you suggest.
SK
Serge Krauss